Azito’s shareholders (Globeleq & IPS)issued the Notice of Proceed with construction in February 2013 to expand and convert the existing plant from a single-cycle power plant to a more efficient combined cycle power plant. This will increase the capacity of the plant by 50% to approximately 420 MW without the need for additional gas or producing any additional CO2 emissions.
| Location | Cote d'Ivoire |
|---|---|
| Description | Azito Expansion |
| Fuel Type | Natural Gas |
| Capacity | 140 MW (Total plant = 420MW) |
| Present status of development | Construction |